CITY OF COLTON
<br /> PUBLIC WORKS DEPARTMENT-ENGINEERING DIVISION
<br /> DATE: September 25,2023
<br /> FROM: Victor P.Ortiz,P.E.,City Engineer
<br /> TO: Matich Corporation
<br /> P.O.Box 10,Highland,CA 92346
<br /> FY 22/23 Asphalt Paving Project
<br /> CONTRACT CHANGE ORDER NO.1
<br /> INSTRUCTIONS TO THE CONTRACTOR AT THE REQUEST OF THE CITY ENGINEER:
<br /> These modifications will add South La Cadena Dr.(Litton to So.Of Tropica Rancho)and F Street(Mt.Vernon to La Cadena)to the project.
<br /> I.INCREASED QUANTITY
<br /> Item No. Description of Work Quantity Unit Unit Cost Total Cost
<br /> A. F Street
<br /> 1 1.5"Grind 136221 SF $ 0.33 = $ 44,952.93
<br /> 2 Rubberized Asphalt 1235 Tons $ 130.00 = $ 160,550.00
<br /> 3 Traffic Loops 5 Ea. $ 970.00 = $ 4,850.00
<br /> 4 Adjust Manhole to Grade 3 Ea. $ 1,360.00 = $ 4,080.00
<br /> 5 Adjust Valve to Grade 3 Ea. $ 125.00 = $ 375.00
<br /> 6 Centerline Ties 4 Ea. $ 420.00 = $ 1,680.00
<br /> 7 Striping and Markings 1 LS $ 6,200.00 = $ 6,200.00
<br /> SUBTOTAL = $ 222,687.93
<br /> B.La Cadena Drive
<br /> 1 2"Grind 18590 SF $ 0.68 = $ 12,641.20
<br /> 2 Rubberized Asphalt 225 Tons $ 148.00 = $ 33,300.00
<br /> 3 Traffic Loops 6 Ea. $ 810.00 = $ 4,860.00
<br /> 4 Adjust Manhole to Grade 2 Ea. $ 1,360.00 = $ 2,720.00
<br /> 5 Adjust Valve to Grade 1 Ea. $ 125.00 = $ 125.00
<br /> 6 Striping and Markings 1 LS $ 7,200.00 = $ 7,200.00
<br /> SUBTOTAL = $ 60,846.20
<br /> TOTAL = $ 283,534.13
<br /> II.DECREASED QUANTITY
<br /> Item No. Description of Work Quantity Unit Unit Cost Total Cost
<br /> SUB-TOTAL = $ -
<br /> TOTAL AMOUNT OF CHANGE ORDER#1 = $ 283,534.13
<br /> III.CONTRACT AMOUNT RECONCILLATION
<br /> ORIGINAL AMOUNT OF CONTRACT = $ 2,503,137.00
<br /> CHANGE ORDER NO.1 = $ 283,534.13
<br /> TOTAL COST OF CONTRACT AS PER CHANGE ORDER NO. 1 = $ 2,786,671.13
<br /> The amount of the contract will be increased by the sum of$283,534.13.and the contract time shall be extended by 0 calendar days. The undersigned
<br /> Contractor approves the foregoing Change Order#1 as to the changes,if any,in the contract price specified for each item including any and all supervision costs
<br /> and other miscellaneous costs relating to the change in work,and as to the extension of time allowed,if any,for completion of the entire work on account of said
<br /> Change Order#1.The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of the directly or indirectly related to
<br /> the approved time extension,required to complete the Change Order items. This document will become a supplement of the contract and all provisions will apply
<br /> hereto. It is understood that the Change Order shall be effective when approved by the Owner.
<br /> Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies,waives,and releases the Owner from all claims,
<br /> demands,costs,and liabilities,in Contract,law or equity,arising out of or related to the subject of the change order,whether known or unknown,including but not
<br /> limited to direct and indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as any and all
<br /> consequential damages.
<br /> Brian Dickinson,Public Works/Utilities Director DATE
<br /> William R.Smith,City Manager DATE
<br /> Matich Corporation DATE
<br /> 1 of 1