November. Staff formally bid this public project as required by the city's Purchasing Ordinance
<br />Section 3.08.050(c). The project was advertised starting November 5, 2007 and as advertised the
<br />bid opening date was December 12, 2007. Staff received the following twenty-eight (28) bids for
<br />this project:
<br />1. Harris Construction
<br />$673,931.00
<br />2. McKenna Construction
<br />$777,000.00
<br />3. SUKUT Construction
<br />$839,224.50
<br />4. American Pride
<br />$850,149.70
<br />5. TC Construction
<br />$859,459.50
<br />6. Beador Construction
<br />$892,700.00
<br />7. H&H Gen Contractor
<br />$898,540.00
<br />8. Grand Pacific
<br />$907,978.50
<br />9. GCI Construction
<br />$913,308.15
<br />10. Vance Corporation
<br />$925,481.05
<br />11. GK Backlund
<br />$967,810.07
<br />12. SOL Construction
<br />$1,051,596.00
<br />13. Riverside Construction
<br />$1,063,920.92
<br />14. Adams Mallory
<br />$1,075,603.00
<br />15. GB Cooke, Inc
<br />$1,116,304.00
<br />16. American Contracting
<br />$1,129,861.25
<br />17. LT Engineering
<br />$1,139,506.60
<br />18. SJ&B Group
<br />$1,144,230.00
<br />19. Abbott Contracting
<br />$1,196,387.00
<br />20. SRD Engineering
<br />$1,273,984.00
<br />21. Metro Builders
<br />$1,359,777.71
<br />22. Highlight Electric
<br />$1,439,644.00
<br />23. LD Anderson
<br />$1,470,737.00
<br />24. NCCI Base, Inc
<br />$1,490,836.00
<br />25. Norstar Engineering
<br />$1,521,363.00
<br />26. SSC Construction
<br />$1,584,922.17
<br />27. Belczak & Sons
<br />$2,044,485.00
<br />28. SD Pazargad
<br />Late Bid (not opened)
<br />Staff recommends the award of a
<br />construction agreement to the lowest responsive and responsible
<br />bidder, Harris Construction, in the
<br />amount of $673,931.00.
<br />ENVIRONMENTAL IMPACT:
<br />The County of San Bernardino has completed an Environmental Impact Report and adopted a
<br />Negative Declaration for the Randall Basin Project completing the California Environmental
<br />Quality Act (CEQA) requirements for the Randall Basin Project. In addition, a Nation Wide Permit
<br />was issued by the Department of the Army Corps of Engineers which complies with the federal
<br />environmental requirements for a project as established by the National Environmental Policy Act
<br />(NEPA).
<br />
|